Answer:
$62
Explanation:
Let the shop's charge per hour for labor = x
If the repair of Victoria's car took 2 hours, then:
• Charge for labour = 2.5x
The cost of the part needed = $93
Therefore, the total charge = 2.5x+93
Since her total bill was $248, we have that:
[tex]2.5x+93=248[/tex]We solve the equation above for x.
[tex]\begin{gathered} 2.5x=248-93 \\ 2.5x=155 \\ \frac{2.5x}{2.5}=\frac{155}{2.5} \\ x=62 \end{gathered}[/tex]The repair shop's charge per hour for labor is $62.