contestada


5. Agency issued RFQ (request for quote) for a contractor to provide program analysis and strategic support (PASS) to identify
technology, operational support and improvement of programs. The contractor needs an understanding of agency's
technologies, projects, programs, practices, policies and procedures and the ability to promptly respond to challenging and
changing requirements. The RFQ contemplated a single-award under a fixed-price, time-and-material or hybrid task order. The
award would be 1-year base and four 1-year option period with an estimated value of $350M. If you are the Co what
evaluation factor would you include in the RFQ and why? Include both Price and non-price factors and their respective level of
importance and ranking.
Student Success
Center
M. Louis Salmon
Submit Assignment

Respuesta :

The evaluation factors, based on their respective rankings (with 1 as the highest and 5 as the least), that the RFQ Committee must include in the RFQ are as follows:

  1. Technical capabilities (to prove the contractor's understanding of the agency's technologies)
  2. Vendor experience (to prove the contractor's understanding of the agency's programs, practices, policies, and procedures.)
  3. Project approach (to prove the contractor's ability to respond to challenges.)
  4. Total contract cost (shows the contractor's understanding of requirements.)
  5. Customer's past Turnover (to ensure the contractor's ability to execute the contract.)

What are RFQ evaluation factors?

RFQ evaluation factors are the criteria that an RFQ committee can use to determine the competing proposals submitted in response to an RFP that would best meet the agency's requirements.

RFQ means Request For Quotation.  RFQs are regularly used to determine the contractor that makes the best contract proposal.

Learn more about RFQ evaluation criteria at https://brainly.com/question/16736391