A consultant has been hired to redesign a company's production facility. The consultant estimates the probabilities of her potential profit as shown in the table below. What is her profit expectation?

Answer:
Step-by-step explanation:
40000*.06+30000*.2+20000*.5+10000*.2+5000*.04= 20600