homework libABC Inc. uses a machine that can produce 95 cranks per hour. The firm operates 9 hours per day, six days per week. Due to regularly scheduled preventive maintenance, the firm expects the machine to be running during approximately 90% of the available time. Based on experience with other products, the firm expects to achieve an efficiency level for the cranks of 80%. What is the expected weekly output of cranks for this company

Respuesta :

The expected weekly cranks output should be 3,693.60.

The following formula should be applied:

= Number of cranks produced per hour × number of hours operated per day × number of days per week × expected machine running percentage × efficiency level

= 95 × 9 × 6 × 90% × 80%

= 3,693.60

Therefore we can conclude that The expected weekly cranks output should be 3,693.60.