On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows:

January 1, 2018 $334,000
September 1, 2018 $498,000
December 31, 2018 $498,000
March 31, 2019 $498,000
September 30, 2019 $334,000


Dreamworld had $6,600,000 in 12% bonds outstanding through both years. Dreamworld's average accumulated expenditures for 2018 was:________

a. 500,000
b. 668,000
c. 583,500
d. 334,000