Answer:
The appropriated answer will be "$1,700,000".
Explanation:
Revenue understood by completion percentage = Design balance throughout progress = $200,000
The percentage completion throughout the whole year will be:
⇒ [tex]\frac{200,000}{2,000,000 }[/tex]
⇒ [tex]10 \ percent[/tex]
The cost incurred throughout the whole year will be:
⇒ [tex]Revenue \ recognized - Income \ on \ the \ contract[/tex]
⇒ [tex]200,000 - 30,000[/tex]
⇒ [tex]170,000[/tex] ($)
Now,
The total estimated cost of the project at the end the year 2021 will be:
⇒ [tex]\frac{170,000}{10 \ percent}[/tex]
⇒ [tex]1,700,000[/tex] ($)