Answer:
Work in process= $20,300
Explanation:
Giving the following information:
October:
$3,300 of direct materials
$6,800 to finish the job.
The company applies overhead at the end of each month at a rate of 150% of the direct labor cost.
To calculate the cost for October, we need to allocate overhead and all 3 components.
Work in process= 3,300 + 6,800 + (6,800*1.5)
Work in process= $20,300