Answer:
A.3257 towels
B.325 towels
Explanation:
A.
d=977 bath towels per day
standard deviation =100 towels per day
Lead time= 3 days
97% Service level = 1.88
Hence:
977*3+1.88*100√3
=2931+1.88*173
=2931+325.24
=3256.24
Approximately 3257 towels
The reorder point is 3257 towels
B.
1.88 ×100√3
=1.88×173
=325 towels
The safety stock is 325 towels