The Flapjack Corporation had 7,872 actual direct labor hours at an actual rate of $12.21 per hour. Original production has been budgeted for 1,100 units, but only 984 units were actually produced. Labor standards were 7.1 hours per completed unit at a standard rate of $13.00 per hour. Round your answer to the nearest cent. The labor time variance is: