Jasper Carts manufactures custom carts for a variety of uses. The following data have been recorded for Job 651, which was recently completed. Direct materials used cost $8.200. There were 179 direct labor hours worked on this job at a direct labor wage rate of $28.00 per hour. There was 90 machine hours used pm this job. The predetermined overhead rate is $3700 per machine hour used. What is the total manufacturing cost of Job 651? $5, 012 $8, 469 $3, 330 $16, 542

Respuesta :

Answer:

The correct answer is D.

Explanation:

Giving the following information:

The direct materials used cost $8.200. There were 179 direct labor hours worked on this job at a direct labor wage rate of $28.00 per hour. There were 90 machine hours used pm this job. The predetermined overhead rate is $37.00 per machine hour used.

Total cost:

Direct material= 8,200

Direct labor= 179*28=5,012

MOH= 37.00*90= 3,330

Total= $16,542