Santoyo Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below:

Hours

Wait time

28.0

Process time

1.0

Inspection time

0.4

Move time

3.2

Queue time

5.1

The delivery cycle time was:

A) 8.3 hours

B) 3.2 hours

C) 37.7 hours

D) 36.3 hours

Respuesta :

Answer:

C) 37.7 hours

Explanation:

It is a time period which shows a delivery time to dispatch the product to the end consumer

The computation of the throughput time is shown below:

= Wait time +  Move time + Queue time + Process time + Inspection time

= 28 + 3.2 + 5.1 + 1.0 + 0.4

= 37.7 hours

It is a combination of the wait time, move time, queue time, process time, and the inspection time.

All other information which is given is not relevant. Hence, ignored it