You are near the end of a sprint when a stakeholder identifies some additional requirements they would like to include. What should youdo ?
A. Add the requirement to the product backlog
B. Decline the request because you are near the end of the sprint
C. Implement the additional requirement
D. Perform an impact analysis and send a change request to the change control board