The Developers forecast that 5 out of 12 items they have in the Sprint Backlog won't be done by the end of the Sprint. What should they do?
a. Review the work with the Product Owner to see if any adjustments are required, and keep working.
b. The remaining items will be moved to the next Sprint Backlog.
c. Continue to the next Sprint without a Sprint Review meeting and finish those items in the next Sprint.
d. Extend the duration of the Sprint, to be able to deliver everything.