contestada

Bashar the project manager of a machine learning automation project. Bashar and the project team have just completed developing the baseline schedule and schedule network diagram for the project. The critical path activities include building a neural network analysis function. While not on the critical path, another activity related to random forest analysis is a key component of the project. With limited team members who are highly skilled with many others who are relatively inexperienced, what is considered the best course of action when Bashar is assigning resources as the project manager? O a. Assign half the skilled resources to the neural network analysis and the other half to the random forest analysis. Assign inexperienced staff to all other tasks not on the critical path. O b. Assign inexperienced staff with the neural network analysis which is on the critical path. Assigned skilled resources to the random forest analysis and other activities. O c. Do nothing - resource allocation and critical path have nothing in common O d. Assign all the skilled resources to neural network analysis which is on the critical path. Assigned inexperienced resources to the random forest analysis as it is not on the critical path.