The project information for the custom order project of the Air Control Company is presented here. Draw a project network for this project. Compute the early and late activity times and the slack times. identify the critical path
ID Activity Predecessor Time
A Order review None 2
B Order standard parts A 15
C Produce standard parts A 10
D Design custom parts A 13
E Software development A 18
F Manufacture custom hardware C, D 15
G Assemble B, F 10
H Test E, G 5
1. Draw a project network for this project. 2. Compute the early and late activity times and the slack times. 3. Identify the critical path. 4. How long will the project take?