1. Which of the following is true of Iteration Goals in SAFe?

They provide KPIs for tracking progress and value realization

They enable teams to keep aligned with PI objectives

They describe the value of planned Features and Enablers

They provide quantifiable metrics to be used in retrospectives

2. Some teams are having difficulty identifying where they might make process improvements. How might the RTE support them?

Run longer I&A meetings to brainstorm improvement items

Encourage the team to perform regular self-assessments and discuss findings

Observe the team's ceremonies and share observations

Conduct a survey to identify the worst problems the team is having

3. Which tool is typically not used during the problem solving workshop?

Pareto analysis

Fishbone diagram

Modified Fibonacci

Dot voting

4. Which statement is true about using a Program Kanban system?

WIP limits are used to provide any needed buffers

Work is pushed through the Kanban to ensure train capacity is utilized

The board tracks features, dependencies and milestones

All work is visualized, progress is continually tracked

5. During the management review and problem-solving meeting, one team raises the risk of not finishing a Feature before the end of the Program Increment (PI). How can the management team help ensure they complete the Feature within the PI?

Redefine the definition of done for Features

Negotiate a reduction in scope of the Feature

ROAM the risk appropriately

Use buffer resources as a guard band

6. During the management review and problem-solving meeting, one team raises the risk of not finishing a Feature before the end of the Program Increment (PI). How can the management team help ensure they complete the Feature within the PI?

Redefine the definition of done for Features

Negotiate a reduction in scope of the Feature

ROAM the risk appropriately

Use buffer resources as a guard band